Event#: | 655 |
Date: | 2019-06-15 |
Agency: | State Parks |
Trail: | BBT Kiosk Projects |
Leader: | Barry Dydyk |
Hours: | 150 |
Volunteers: | 20 |
Distance: | 100 |
Status: | Completed |
Regulars: | 2 |
Casuals: | 18 |
pdf: | 20190615BBT-TH_Improvements.pdf |
CSUCI: | 0 |
Tag: | MCSP, BBT,BBT_Improvements |
Previous Events
ID |
Date |
Leader |
Hours |
724 | 2020-02-15 | Jerry Mitcham | 21.5 |
656 | 2019-06-16 | Barry Dydyk | 44.0 |
655 | 2019-06-15 | Barry Dydyk | 150.0 |
583 | 2018-08-01 | Jerry Mitcham | 113.0 |
533 | 2017-12-02 | Jerry Mitcham | 26.0 |
526 | 2017-11-18 | Barry Dydyk | 90.5 |
Crew Member |
Hours |
Barry Dydyk | 7.50 |
Jerry Mitcham | 7.50 |
The project is part of the SMMTC BBT Trail Head Improvement project and improved THs at Tapia Park and the hairpin turn on Piuma Rd. On Saturday we met the candidate at Malibu Creek and loaded a picnic table and a kiosk onto Jerry's truck and transported them to the Piuma TH at the hairpin turn. We installed the kiosk legs by digging two post holes 30 inches deep, aligning them and pouring cement. We also prepared a pad for the picnic table, assembled the table and installed a cable to secure the table. We also prepared the table pad at theTapia TH. This effort involved 6 adults and 14 scouts and took 7.5 hours