× Home Crew Stats-old version Trail Stats Work Schedule Agency Report by Years Crew - Year by Year Totals Crew - Stats - XTAB Crew Accomplishments
Event#:925
Date: 2023-02-04
Agency:State Parks
Trail: Saddle Creek
Leader:Greg Sweel
Hours: 132
Volunteers:22
Distance:3432
Status: Completed
Regulars: 17
Casuals: 5
pdf:20230204LowerSaddleCreek.pdf
CSUCI: 0
Tag:MCSP, CSUCI_TC
Previous Events on this Trail
ID Date Leader Hours
9392023-04-04Jerry Mitcham54.0
9372023-03-24Jerry Mitcham6.0
9292023-02-18Barry Dydyk90.0
9282023-02-11Anne Russell84.0
9252023-02-04Greg Sweel132.0
7192020-01-25Jerry Mitcham36.0
7072019-11-23Greg Sweel192.0
6492019-05-25Jerry Mitcham54.0
6342019-04-13Greg Sweel38.5
6302019-03-30George Sherman72.0
4992017-06-28Dave Edwards42.0
4972017-06-17Jerry Mitcham60.0
4642017-02-11Dave Edwards48.0
4102016-03-05Barb Thomas60.0
3262015-05-02Greg Sweel24.0
2202014-04-05Greg Sweel48.0
1802013-10-12Greg Sweel30.0
532012-03-3172.0
352012-02-0483.5
32011-09-1735.0
Crew Member Hours
Anne Russell6.00
Barry Dydyk6.00
Bridgette Bagheri6.00
Dave Edwards6.00
Denise Pomonik6.00
George Sherman6.00
Greg Sweel6.00
Jerry Mitcham6.00
John Kross6.00
Jon Sheldon6.00
Kirsten Rosselot6.00
Lauren Schneider6.00
Michael Harmon6.00
Robert Bittner6.00
Ruth Feldon6.00
Solomon Adams6.00
Viviana Celaya6.00
Location: Lower Saddle Creek Trail (BBT) Malibu Creek State Park Crewleader: Greg Sweel Summary: This was a routine planned trail maintenance event and the first of three consecutive projects on this trail. A crew of 22 met near the trailhead where the Piuma Ridge Trail (BBT) crosses Piuma Road at 8:30 am. After signing-in and having a safety talk we distributed tools and proceeded up the trail. The crews broke into groups with one group of six working on the initial 100 yards to fill in an erosional rut and brush the edges to restore the 4-foot trail width. Another group followed one of the two hedge trimmers down and across Dark Canyon to clean cuttings, widen the trail, remove rocks, and cut overhead branches. Another hedge trimmer worked down to the creek crossing and continued further up restoring a well-groomed trail corridor. Others cleared brush/vegetation, removed slough, widened the trail, and cleaned up the cuttings using McLeods, loppers, pick-mattocks, and folding hand saws. We made good progress and ended work at 1:15 pm and then cached the tools for next Saturday’s return. We all hiked down the trail to Piuma Road and arrived back at our meeting place at 2:30 pm. We cleared approximately 0.65 miles. There are some recent rain-related erosional problems just beyond where we left off and will try to address them in the upcoming 2 work events as we continue to clear this trail of brush and improve the badly worn and eroded tread. Crew size: 22 Total Hours worked: 132 hours total (22 volunteers 6 hours each) Total feet of trail maintained: 3432 feet (0.65 miles) Crew Members: Dave Edwards, Jerry Mitcham, Barry Dydyk, George Sherman, Jon Sheldon, Ruth Feldon, Greg Sweel, Bridgette Bagheri, Lauren Schneider Solomon Adams, Kirsten Rosselot, Anne Russell, Denise Pomonik, Viviana Celaya, Robert Bittner, Desirae Renta, John Kross, and 5 other volunteers.
2 images, scroll down to see susbsequent images.image from our trail work eventimage from our trail work event