Event#:942
Date: 2023-04-15
Agency:State Parks
Trail: Dead Horse Trail
Leader:Don Brusselars
Hours: 72
Volunteers:12
Distance:1320
Status: Completed
Regulars: 12
Casuals: 0
pdf:20230415DeadhorseTrail.pdf
CSUCI: 0
Tag:TSP, BBT
Previous Events on this Trail
ID Date Leader Hours
9422023-04-15Don Brusselars72.0
9412023-04-08Jerry Mitcham72.0
9402023-04-06Jerry Mitcham7.5
9362023-03-27Jerry Mitcham2.5
712012-03-1078.0
Crew Member Hours
Barry Dydyk6.00
Carlyn Taggart6.00
Dave Edwards6.00
Denise Pomonik6.00
Don Brusselars6.00
Greg Sweel6.00
Jerry Mitcham6.00
John Kross6.00
John Reynolds6.00
Jon Sheldon6.00
Jon Van Gorder6.00
Ruth Feldon6.00
A group of twelve volunteers assembled at Dead Horse Parking lot, and one small group weed-whipped the trail from the parking lot down to Topanga Canyon Blvd, approximately 350 feet. After they finished they joined us further up the trail. The remainder hiked up the trail about 0.2 mile and commenced work, which consisted of cutting and clearing the brush on the edges of the trail, doing tread work where the water had damaged the trail, installed barriers and drains to prevent further erosion, filled in the area between steps that were eroded, and cleaned out an existing drainage that ran along side the trail (maybe 3 ft wide and 3 ft deep_ that had apparently got clogged and overflowed on to the trail and contributed to substantial erosion. Approximately 750 feet of trail were cleared, groomed and repaired in this section. Hiked back to parking about 2:30 p.m. 12 volunteers @ 6 hours for a total of 72 hours Approximately 1/4 mile of trail was weed-whipped, cleared and repaired.
image from our trail work event