Event#: | 945 |
Date: | 2023-05-02 |
Agency: | State Parks |
Trail: | Malibu Creek Bridge |
Leader: | Dave Edwards |
Hours: | 54 |
Volunteers: | 9 |
Distance: | 100 |
Status: | Completed |
Regulars: | 9 |
Casuals: | 0 |
pdf: | 20230502MalibuCreek.pdf |
CSUCI: | 0 |
Tag: | TSP |
Previous Events on this Trail
ID |
Date |
Leader |
Hours |
945 | 2023-05-02 | Dave Edwards | 54.0 |
Crew Member |
Hours |
Barb Thomas | 6.00 |
Carlyn Taggart | 6.00 |
Dave Edwards | 6.00 |
Denise Pomonik | 6.00 |
Don Brusselars | 6.00 |
John Reynolds | 6.00 |
Jon Sheldon | 6.00 |
Juan Carlos Mendoza | 6.00 |
Ruth Feldon | 6.00 |
We met at 7:30 at the Blandings house at Malibu Creek State Park. We had a good turnout with nine of our Trails Council volunteers, four or so from the Malibu Creek SP docents and Jason plus two of his people. The main objective today was to install a 20 foot aluminum bridge across Malibu Creek where the portion of the creek eroded away from one end of the concrete bridge leaving a gap of about 17 ft. We loaded the bridge onto a truck a drove it to the installation site. With help of several people on each side of the creek, the bridge was placed in position and anchored on both sides. We then installed some 28 or so wooden planks on the bridge thus completing the project.
We also improved the trail from the end of the installed bridge for about 100 ft clearing dense brush and performing tread work.
Crew size: 9
Hours worked: 6
Total hours worked: 54
Feet of trail cleared: N/A
Crew members: Dave Edwards, Jon Sheldon, Ruth Feldon, Denise Pomonik, Carlyn Taggart, John Reynolds, Juan Carlo, Barb Thomas and Cindy Kimmick