Single Event Record Display
× Home Crew Stats-old version Trail Stats Work Schedule Agency Report by Years Crew - Year by Year Totals Crew - Stats - XTAB Crew Accomplishments
Event#:1007
Date: 2023-10-28
Agency:State Parks
Trail: Upper Sycamore
Leader:George Sherman
Hours: 72
Volunteers:12
Distance:3500
Status: Completed
Regulars: 12
Casuals: 0
pdf:20231028UpperSycamore.pdf
CSUCI: 0
Tag:PMSP
Previous Events on this Trail
ID Date Leader Hours
10072023-10-28George Sherman72.0
9042022-10-28Jon Sheldon7.0
8302021-12-02John Kross9.0
7802021-01-02John Kross6.0
7642020-10-24John Kross65.0
7632020-10-17John Kross48.0
7122019-12-27George Sherman6.0
6222019-02-27Dave Edwards54.0
6062018-12-01Jerry Mitcham18.0
6002018-10-13John Kross3.0
5592018-04-25Norm Simmonds18.0
5272017-11-28Jerry Mitcham30.0
5282017-11-16John Kross42.0
5252017-11-14Barry Dydyk36.0
5212017-11-09Jerry Mitcham48.0
5202017-11-07John Kross30.0
5222017-11-02Dave Edwards24.0
5232017-10-31Barry Dydyk24.0
5182017-10-26Jerry Mitcham30.0
5142017-10-19Dave Edwards4.0
5022017-07-29John Kross16.0
5012017-07-19Jerry Mitcham25.0
5002017-07-06Dave Edwards30.0
4892017-05-17John Kross16.0
4732017-03-25Dave Edwards66.0
4652017-02-23Dave Edwards10.0
4582017-01-18Norm Simmonds60.0
4172016-06-24Dave Edwards20.0
4132016-06-08Norm Simmonds38.5
3902016-03-15Norm Simmonds9.0
3762016-01-16Dave Edwards54.0
3752016-01-09Dave Edwards66.0
3422015-06-27Norm Simmonds48.0
3362015-06-13John Kross36.0
2162014-03-19Norm Simmonds42.0
1582013-07-1613.5
1432013-05-1548.0
1652013-04-21203.0
Crew Member Hours
Carlyn Taggart6.00
Christopher Ramirez6.00
Dave Edwards6.00
George Sherman6.00
Greg Sweel6.00
Jerry Mitcham6.00
Jon Sheldon6.00
Jon Van Gorder6.00
Kirsten Rosselot6.00
Norm Simmonds6.00
Ruth Feldon6.00
Sharon Simmonds6.00
The SMMTC trail crew and a CSUCI Trail Corp volunteer met at the Wendy & Potrero trailhead. Project briefings and safety talk were presented. We discussed ways to clear the trail and maintain existing widths. There was a substantial amount of non-native grass to be dealt with. Shuttled into the park in 3 vehicles. Handed out tools and placed crew into 3 groups. Norm & Sharon, Greg, George & Dave worked the first quarter mile of trail. Brush was trimmed and removed. Other crew members walked up to the point we left off in April. Greg, George & Dave worked their way up the trail to where the rest of the crew was working. Greg, Christopher and Jon van Gorder leapfrogged up the trail. Kirsten, Ruth, Jon Sheldon, & Carlyn tackled many sections of the trail where the grass was encroaching. Lunch was taken alongside the trail – taking advantage of the shade. Resumed work. We did our best to trim encroaching grasses & brush but refrained from removing too much brush. We kept the trail narrow in many spots and where the trail spread out a bit on the older roadbed did our best to not widen excessively. One existing drain was cleared of silt. Returned to vehicles. Total volunteer hours: 12 Volunteers x 6.0 hours = 72.0 hours Feet of trail maintained: 3,500
Crew: Ruth Feldon, Dave Edwards, Jon Sheldon, Carlyn Taggart, Greg Sweel, Jon Van Gorder, Jerry Mitcham, Kirsten Rosselot, George Sherman, Norm Simmonds, Sharon Simmonds