Event#: | 462 |
Date: | 2017-01-25 |
Agency: | NPS |
Trail: | Saddle Peak - Spanish Broome |
Leader: | Jerry Mitcham |
Hours: | 12 |
Volunteers: | 4 |
Distance: | 1500 |
Status: | Completed |
Regulars: | 4 |
Casuals: | 0 |
pdf: | 20170125SaddlePeakRestoration.pdf |
CSUCI: | 0 |
Tag: | SPSB |
Previous Events
ID |
Date |
Leader |
Hours |
657 | 2019-06-19 | Jerry Mitcham | 36.0 |
568 | 2018-06-20 | Jerry Mitcham | 24.0 |
498 | 2017-06-14 | Jerry Mitcham | 42.0 |
462 | 2017-01-25 | Jerry Mitcham | 12.0 |
344 | 2015-07-25 | Jerry Mitcham | 46.0 |
311 | 2015-03-25 | Jerry Mitcham | 6.0 |
168 | 2013-08-17 | | 18.0 |
156 | 2013-07-20 | | 19.5 |
155 | 2013-06-29 | | 25.0 |
128 | 2013-02-23 | | 30.0 |
122 | 2013-01-19 | | 30.0 |
119 | 2012-12-15 | | 24.0 |
102 | 2012-11-21 | | 24.0 |
113 | 2012-11-03 | | 7.0 |
111 | 2012-10-27 | | 12.0 |
78 | 2012-09-22 | | 24.0 |
73 | 2012-08-25 | | 18.0 |
Crew Member |
Hours |
Barry Dydyk | 3.00 |
Dave Edwards | 3.00 |
Ed Pushich | 3.00 |
Jerry Mitcham | 3.00 |
John Kross | 3.00 |
This was a scheduled project. The object of this project was to perform Spanish Broom removal on Saddle Peak. There were 5 SMMTC volunteers present. Met at the BBT trail head on Stunt Road. Held tool talk and safety briefings. Hiked up to the meadow above the water tank. Treated approximately one acre of infested area using the “cut and paint” technique. There was not a lot a broom in this area. Upon completion of broom treatment, we performed some trail maintenance on the BBT. Removed some fallen limbs cross the trail and cleaned all the drains.. .Finished work and hiked back to the trailhead. Total volunteer hours: 5 Volunteers x 3 hours = 15 hours Feet of trail maintained: 1,500