Event#: | 924 |
Date: | 2023-02-01 |
Agency: | State Parks |
Trail: | Serrano Valley Trails |
Leader: | Dave Edwards |
Hours: | 54 |
Volunteers: | 9 |
Distance: | 950 |
Status: | Completed |
Regulars: | 9 |
Casuals: | 0 |
pdf: | 20230201SerranoValley.pdf |
CSUCI: | 0 |
Tag: | PMSP |
Previous Events on this Trail
ID |
Date |
Leader |
Hours |
930 | 2023-02-22 | Dave Edwards | 25.0 |
924 | 2023-02-01 | Dave Edwards | 54.0 |
922 | 2023-01-28 | Don Brusselars | 78.0 |
920 | 2023-01-25 | Dave Edwards | 54.0 |
921 | 2023-01-21 | John Kross | 72.0 |
923 | 2023-01-18 | John Kross | 16.0 |
913 | 2022-12-10 | John Kross | 40.0 |
911 | 2022-12-03 | Dave Edwards | 91.0 |
910 | 2022-12-01 | Jon Sheldon | 5.0 |
Crew Member |
Hours |
Carlyn Taggart | 6.00 |
Dave Edwards | 6.00 |
Denise Pomonik | 6.00 |
George Sherman | 6.00 |
Jerry Mitcham | 6.00 |
Jon Sheldon | 6.00 |
Norm Simmonds | 6.00 |
Ruth Feldon | 6.00 |
Sharon Simmonds | 6.00 |
We met at 8:30 at Serrano and Cotharin roads and drove to the end of Serrano Road. We hiked about 0.8 miles to begin work where we left off last time. We cleared about 100 ft of brush down to the creek crossing. So, this section of trail is cleared from near the old ranch site to the creek. Just across the creek we did tread work for some 150 ft of trail. Backtracking about 200 ft from the creek crossing, we used one weed whacker to re-establish the old trail from the intersection of the Serrano Valley loop trail (near the lower creek crossing) to the water pipe which crosses the same creek about 700 ft. upstream. One more outing will be required to finish re-establishing all of these trails. It will be mostly weed whacking about 300 ft of grass to join up with the main valley trail.
Crew size: 9
Hours worked: 6
Total hours worked: 54
Feet of trail cleared: 950
Crew members: Dave Edwards, Jerry Micham, Jon Sheldon, Ruth Sheldon, Denise Pomonik, George Sherman, Carlyn Taggart, Norm and Sharon Simmonds